The new Silverton Civic Center under construction. James Day

Civic center delays – Silverton project still under $19.5M budget

By James Day The new Silverton Civic Center will not be occupied until next spring.  The $19.5 million project, which originally was projected to open in July 2023, has experienced a steady stream of delays, including supply chain issues, work that had to be redone and even emails that went missing.  The project remains under that $19.5 million overall cost, […]

Final steps – Silverton accepts bid for civic center construction

By James Day Silverton will break ground on its new civic center this spring, with opening tentatively set for summer 2023. The City Council selected Corp Inc. of Salem as the general contractor at its March 7 meeting. Corp Inc. turned in the winning bid of $14,750,000 to build the center, which will include a two-story civic center/police building as […]